Progress Billing and Retainage: How to Invoice a Big Job in Stages (and Collect the Last Check)

Short answer: On a big job, agree on a schedule of values before you start: the contract price split into lines like demo, framing and finishes. Each billing period, invoice for how far along each line is, minus what you already billed and the retainage the contract holds back. When the punch list is done, invoice the retainage.

A big job doesn't get paid in one check. It gets paid in pieces over weeks or months, and the client usually keeps a slice of every piece until the very end.

That's fine, as long as both sides can see the math. Where it goes wrong is when nobody wrote down what "40% done on framing" is worth, the change orders live in a text thread, and the retainage held back over six months turns into the last check nobody remembers to send.

This is the bigger cousin of milestone billing. If your projects split cleanly into a few stages (deposit, draft, delivery), How to Bill a Project in Milestones is simpler and probably all you need. Progress billing is for jobs where work happens on many fronts at once and the client pays for whatever got done each period.

What is progress billing?

Progress billing means you invoice for the share of the work completed during each period, usually monthly, instead of at fixed stages. Each invoice is sometimes called a pay application or "pay app."

The difference from milestones:

  • Milestones: "Design approved, invoice Milestone 2." A stage is either done or it isn't.
  • Progress billing: "Framing is 75% done, electrical rough-in is 50% done." You bill for how far along each part of the job is.

What is a schedule of values?

It's the contract price broken into lines, agreed before the work starts. Every progress invoice is measured against it.

A simple example for an $80,000 remodel:

  • Demolition: $8,000
  • Framing: $20,000
  • Electrical rough-in: $12,000
  • Plumbing rough-in: $10,000
  • Drywall: $14,000
  • Finishes and trim: $16,000
  • Total: $80,000

(Job, lines and amounts are examples only.)

A few tips:

  • Use lines the client can see on site. "Framing" can be checked by walking the job. "Phase 2 overhead" can't.
  • Don't front-load it. It's tempting to put extra value on the early lines so more cash comes in early. Clients and GCs notice, and it costs you trust on every pay app after.
  • If the client has a form, use theirs. Some general contractors and commercial owners require their own pay application form, often the AIA G702/G703. Ask before the first billing.

What should the contract say?

Before the first progress invoice, get these in writing:

  1. The schedule of values.
  2. The billing period and invoice day. For example, the 25th of each month for work through that date.
  3. How percent complete gets agreed. A site walk, photos, or the GC's sign-off.
  4. Retainage. Whatever percentage the contract sets, and when it gets released: substantial completion, punch list done, final inspection, or something else.
  5. When payment is due after each invoice.
  6. How change orders get added to the schedule.
  7. Any paperwork the client needs with each invoice, such as lien waivers. Forms and rules vary by state.

If the contract has a deposit, send the deposit invoice when the scope is signed, before the first progress bill.

Many states have rules on retainage and on how fast owners and GCs have to pay on construction jobs. They differ a lot, and they change. Check your state's rules; this isn't legal advice.

What goes on a progress invoice?

Everything a normal invoice needs, plus the running numbers. Here's pay app #2 on the example job, covering work through October 25:

  • Demolition: $8,000 value, 100% complete, $8,000 to date
  • Framing: $20,000 value, 75% complete, $15,000 to date
  • Electrical rough-in: $12,000 value, 50% complete, $6,000 to date
  • Plumbing rough-in: $10,000 value, 50% complete, $5,000 to date
  • Drywall: $14,000 value, 0% complete, $0 to date
  • Finishes and trim: $16,000 value, 0% complete, $0 to date

Then the summary:

  • Contract total: $80,000
  • Completed to date: $34,000
  • Less retainage held (at the contract rate; example amount): $1,700
  • Earned to date, less retainage: $32,300
  • Less previously billed (pay app #1): $7,600
  • Amount due this invoice: $24,700, due Nov 24

(All numbers are examples only. Use the retainage rate in your contract.)

That summary is what keeps the client's bookkeeper from emailing you. They can check each line against the last invoice without calling.

Also include:

How do change orders fit in?

Once a change order is signed, add it to the schedule of values as its own line, with its own value and percent complete. Don't fold it into an existing line, or nobody can tell what changed.

For example: "CO #1, add recessed lighting in kitchen, $2,400, 0% complete." The contract total goes up by the same amount, and the next pay app shows it. How to Invoice a Change Order covers getting it signed before you do the work.

How do you get the retainage paid at the end?

Retainage is the easiest money on the job to lose. It sits there for months, the crew moves on, and nobody sends the bill.

  • Track it on every pay app. Keep a running "retainage held to date" number. On the example job, by the last pay app it might be $4,000.
  • Finish the punch list fast and get it signed off in writing. Release usually depends on it, and every week it sits open is a week the retainage sits too.
  • Send a separate retainage invoice the day the release condition is met. One line: "Release of retainage, pay apps #1 through #6: $4,000." Attach or reference the sign-off and any closeout paperwork the contract asks for.
  • Put it on your open list right away. If it isn't paid by the due date, follow up like any other invoice: short, friendly, with the invoice number. How to Track Unpaid Invoices has a tracker you can copy.

What if the client disputes the percent complete?

It happens. You say framing is 75%, they say 60%. Don't hold the whole invoice over one line.

  • Walk the job together or trade photos, and agree on a number.
  • Revise that line and resend the invoice with the same pay app number, marked "revised."
  • Bill the difference on the next pay app once the work is clearly there.

The lines nobody disputes should still get paid on time.

How does this work in InvoiceMedley?

In InvoiceMedley you create a professional invoice in minutes. For a progress bill, add one line item per schedule-of-values line with the amount for this period. Put the running summary (contract total, completed to date, retainage held, previously billed) in the email that carries the invoice, or send your spreadsheet along with it. Email the invoice with the PDF attached, and the client can pay right away with Pay Now through your own connected Stripe account. Send the retainage as its own invoice at the end.

Keep the schedule of values itself in a simple spreadsheet. Built-in change orders and automatic payment reminders are coming soon. Until then, you add change orders as line items and follow up by hand.

Plans are $19 a month for Starter, $49 for Professional and $99 for Enterprise.

Frequently asked questions

What's the difference between progress billing and milestone billing?

Milestone billing sends an invoice when a stage is finished. Progress billing sends an invoice each period for how far along each part of the job is. Milestones suit projects with a few clear stages; progress billing suits big jobs with work happening on many fronts.

What is retainage?

Retainage is a part of each payment the client holds back until the job is finished, as a guarantee the work gets completed. The amount is whatever percentage the contract sets, and it's paid out when the release condition in the contract is met.

How do I invoice for retainage?

Send a separate invoice for the total retainage held once the release condition (often the punch list or final sign-off) is met. Reference the pay apps it came from and attach any paperwork the contract requires.

Do I need a schedule of values for a small job?

Usually not. If the job has a few clear stages, milestone billing is simpler. A schedule of values earns its keep on bigger jobs with many trades or phases running at the same time.

Are there laws on retainage and prompt payment?

Many states have them, and they vary by state and by type of project. Check your state's rules; this isn't legal advice.